* Pre-Application *
PREAPP 2026000056
Project Name: St. Augustine Airport East Terminal Drive
Parent Project:
COMM-2002000015
Issue Date:
4/29/2026
Comp Date:
Applicant:
Matt Singletary /WK (904) 624-0978 /HM (904) 624-0978
Owner:
Proj Desc:
Phase 1 (Infrastructure - East Side Development Areas A & B)
Construction of approximately 1,910 linear feet of new roadway (East Terminal Drive) between Gun Club Rd. and the south end of Hawkeye View Lane (adjacent Northrop Grumman Building 40), including roadway lighting and landscaping. This new road will provide vehicular access to aviation development on the east side of the Airport property. The new roadway is necessary because aviation development requires demolition of a portion of the existing Hawkeye View Lane roadway in order to provide additional space for aviation facilities. This project also includes approximately 1,100 linear feet of new roadway to connect the north end of Hawkeye View Lane to the primary new roadway, East Terminal Drive. Associated work includes stormwater management facilities, utility improvements, wetland mitigation, clearing and filling of Areas A & B within the Airport’s East Side Development Area.
Phase 2 (Hangar Facility Development - East Side Development Areas A & B)
| Date | Time | Note |
|
5/13/2026
|
4:07 PM
|
DRC Confirmed 5/20/2026 10:30-11:00 In Person
Confirmation email uploaded
|
|
5/8/2026
|
9:33 AM
|
Comments Sent to Applicant
|
|
4/29/2026
|
12:44 PM
|
DRC 5/20/2026 / CSA
|