* Commercial *
COMM 2026000008
Project Name: Wells Fargo WGV
Parent Project:
MDP-2026000002
Issue Date:
1/23/2026
Comp Date:
Applicant:
Ryan Hileman /WK /HM (813) 812-4100
Owner:
IGP WCC PROJECT LLC /WK /HM
Proj Desc:
This project proposes the development of a 4,200 SF Wells Fargo Bank and accompanying infrastructure on a 1.20-acre outparcel (Outparcel 2A) within the approved Master Development Plans for Walmart Supercenter #3909-100.
| Date | Time | Note |
|
4/8/2026
|
3:04 PM
|
Third resubmittal 5-day review Signatures verified
|
|
4/8/2026
|
9:29 AM
|
Comments Sent to Applicant
|
|
3/23/2026
|
1:54 PM
|
Comments Sent to Applicant
|
|
3/19/2026
|
8:58 AM
|
Fee Email Sent to Applicant
|
|
3/19/2026
|
8:58 AM
|
Second resubmittal 5-day review
|
|
3/6/2026
|
9:02 AM
|
Comments Sent to Applicant
|
|
2/26/2026
|
7:54 AM
|
First resubmittal 5-day review Signatures verified
|
|
2/13/2026
|
3:27 PM
|
DRC CONFIRMED 2/18/26 2:00-2:30 Teams Meeting Confirmation email uploaded
|
|
2/12/2026
|
8:42 AM
|
Frist submittal 8-day review DRC 2/18/26 SJCU
|
|
2/6/2026
|
10:09 AM
|
Comments Sent to Applicant
|
|
2/5/2026
|
9:45 AM
|
Project Description Updated
|
|
2/4/2026
|
9:36 AM
|
Project Description Updated
|
|
2/2/2026
|
11:59 AM
|
Fee Email Sent to Applicant
|
|
2/2/2026
|
7:50 AM
|
Fee Email Sent to Applicant
|
|
1/30/2026
|
4:05 PM
|
Asbuilt approval will be dependent upon the completion of CR 2209 and Walmart WCC MODCP 2025-118 for access.
|
|
1/23/2026
|
9:34 AM
|
Fee Email Sent to Applicant
|
|
1/23/2026
|
9:28 AM
|
Routed Submittal without receiving payment.
|