* Pre-Application *
PREAPP 2025000117
Project Name: Veritas School Main Campus
Parent Project:
CLTR-2021000102
Issue Date:
9/5/2025
Comp Date:
Applicant:
Kyle Sowards /WK /HM (904) 826-1334
Owner:
David Lee Sellers /WK /HM
Proj Desc:
Redevelopment of eastern section of the property for Veritas School Main Campus.
Existing single-family home will remain and changed to admin building for the school.
Phase 1 includes conversion of admin building, 12 portables in the SW section and 12 portables in the NE section plus a portion of the parking.
Phase 2 includes removal of 12 portables in the NE section and construction of Main Building and remaining parking and sports field.
| Date | Time | Note |
|
10/3/2025
|
1:04 PM
|
DRC CONFIRMED- IN-PERSON 2:00-2:30
|
|
9/24/2025
|
3:58 PM
|
Comments Sent to Applicant
|
|
9/17/2025
|
10:44 AM
|
5-day review DRC 10/8/25
|