| Date | Time | Note |
|
3/3/2026
|
10:47 AM
|
Comments Sent to Applicant
|
|
2/26/2026
|
4:27 PM
|
APPROVAL AND BONDING FOR RW CONST 2025-01 REQUIRED PRIOR TO RELEASE OF COMM 2025-96
|
|
2/26/2026
|
4:15 PM
|
The applicant is aware that the CO for the Grocer/Retail will not be issued until construction of the signalization at Longleaf PIne Pkwy/Knights Lane is permitted, bonded and has commenced construction. The applicant is also aware that appropriate MOT and/or access restriction will be required at the intersection until the signal is operational and will coordinate with SJC to implement as necessary.
|
|
2/26/2026
|
7:39 AM
|
Fee Email Sent to Applicant
|
|
2/26/2026
|
7:38 AM
|
Second resubmittal 5-day review Unable to verify Tim O'Rileys signature
|
|
2/24/2026
|
11:36 AM
|
COMM CO cannot move forward without approval and commencement of construction to for access. Signal plans to be within the next 4-6 months per applicant's engineer.
|
|
2/24/2026
|
8:04 AM
|
Comments Sent to Applicant
|
|
2/23/2026
|
10:51 AM
|
original comp date 02/18/26 opened for environmental
|
|
2/19/2026
|
9:43 AM
|
Comments Sent to Applicant
|
|
2/9/2026
|
11:13 AM
|
DEPENDENCY: The approval of COMM 25-96 As Built is dependent on approval of RWCONST 2025-1 As Built.
|
|
2/4/2026
|
4:30 PM
|
First resubmittal 5-day review Signatures verified
|
|
12/16/2025
|
3:37 PM
|
Signalization of Longleaf Pine Pkwy/Knights Lane intersection must be completed prior to C/O.
|
|
12/11/2025
|
8:01 AM
|
DRC CONFIRMED 12/17/25 1:15-1:45 IN PERSON CONFIRMATION EMAIL UPLOADED
|
|
12/2/2025
|
2:46 PM
|
Comments Sent to Applicant
|
|
11/19/2025
|
3:54 PM
|
Signal Plans required for proposed connection at Longleaf Pine Pkwy/Knights Lane intersection.
|
|
11/10/2025
|
7:42 AM
|
Fee Email Sent to Applicant
|
|
11/10/2025
|
7:41 AM
|
Routed Submittal without receiving payment.
|
|
11/10/2025
|
7:41 AM
|
First submittal10-day review JEA DRC 12/17/25 Signatures verified
|