| Date | Time | Note |
|
12/9/2024
|
11:36 AM
|
FH in NW corner (outside fenced complex) next to Bozard to be slightly relocated per email with Josh Nyberg.
|
|
6/5/2024
|
10:40 AM
|
M2024-002998-44,281 SF Building #1 M2024-002998*001-44,281 SF Building #2 M2024-002998*002-42,099 SF Building #3 M2024-002998*003-44,281 SF Building #4 M2024-002998*004-42,099 SF Building #5 M2024-002998*005- 37,237 SF Building #6 M2024-002998*006-42,099 SF Building #7 M2024-002998*007- 37,237 SF Building #8 M2024-002998*008- 42,099 SF Building #9 M2024-002998*009- 2,542 SF Leasing Office M2024-002998*010-5,029 SF Clubhouse/ Fitness Center M2024-002998*011-1,922 SF Garage #1 M2024-002998*012-1,922 SF Garage #2 M2024-002998*013-4,002 SF Garage #3 M2024-002998*014-3,809 SF Garage #4 M2024-002998*015- 1058 SF Garage #5 M2024-002998*016- 1,922 SF Garage #6 M2024-002998*017-1,922 SF Garage #7 M2024-002998*018-1,922 SF Garage #8 M2024-002998*019- Pool
|
|
6/4/2024
|
3:35 PM
|
sent ERMS link to schrierd@etminc.com
|
|
5/29/2024
|
10:45 AM
|
APPROVED
|
|
5/28/2024
|
2:20 PM
|
Fee Email Sent to Applicant
|
|
5/15/2024
|
7:38 AM
|
Fee Email Sent to Applicant
|
|
5/15/2024
|
7:37 AM
|
Second resubmittal 5-day review Signatures Verified
|
|
3/26/2024
|
9:17 AM
|
Comments Sent to Applicant
|
|
3/19/2024
|
12:44 PM
|
These plans cannot be approved until SMADJ 2024-22 is approved and recorded with Clerk of Courts.
|
|
3/15/2024
|
7:33 AM
|
First resubmittal 5-day review Signatures Verified
|
|
2/5/2024
|
10:46 AM
|
Comments Sent to Applicant
|
|
2/2/2024
|
3:50 PM
|
First submittal 12-day review/ DRC 2/7/24/ SJCU Signatures Verified
|
|
2/2/2024
|
3:16 PM
|
$18,500 Tree Bank Payment Due
|
|
1/17/2024
|
1:36 PM
|
Fee Email Sent to Applicant
|