| Date | Time | Note |
|
8/8/2023
|
10:28 AM
|
Dependency: SUBCON 2021-49 depends on As-Built approval for RWCONST 2021-17
|
|
6/30/2022
|
3:04 PM
|
READY FOR PRE CON MEETING
|
|
4/1/2022
|
3:37 PM
|
emailed FTP link Matthew Melchiori <mmelchiori@prosserinc.com>
|
|
4/1/2022
|
3:29 PM
|
APPROVED printed inspectors copy
|
|
3/31/2022
|
1:28 PM
|
School Concurrency mitigation payment received by the School District on 03/30/2022 in the amount of $355,200.00 for 80 single family dwelling units in Phase 3E
|
|
3/22/2022
|
11:09 AM
|
Comments Sent to Applicant
|
|
3/22/2022
|
11:08 AM
|
Fee Email Sent to Applicant
|
|
3/22/2022
|
11:08 AM
|
NO RESUB UNTIL FEE IS PAID
|
|
3/15/2022
|
1:18 PM
|
Fee Email Sent to Applicant
|
|
3/15/2022
|
1:17 PM
|
Third Resubmittal 5-day review signatures verified
|
|
3/14/2022
|
10:51 AM
|
Comments Sent to Applicant
|
|
3/3/2022
|
7:45 AM
|
Fee Email Sent to Applicant
|
|
3/3/2022
|
7:46 AM
|
Second Resubmittal 5-day review signatures verified
|
|
1/26/2022
|
8:18 AM
|
Comments Sent to Applicant
|
|
1/13/2022
|
1:52 PM
|
First Resubmittal 5-day review
|
|
12/23/2021
|
10:03 AM
|
CIF PAID
|
|
11/18/2021
|
2:44 PM
|
Comments Sent to Applicant
|
|
10/26/2021
|
8:02 AM
|
Fee Email Sent to Applicant
|
|
10/26/2021
|
7:58 AM
|
First Submittal 15-day review/JEA/DRC?
|