Sign In

St. Johns County Application Submittal Management

* Commercial *

COMM   2020000103

Project Name: Chase Bank International Golf Parkway (IGP & SR 16)

Parent Project: MDP-2021000006

Issue Date: 12/22/2020 Comp Date: 3/3/2021 hsapp

Applicant: Atef Hanna   /WK 813-319-8768   /HM 

Owner: Cantrell & Morgan, Inc.   /WK    /HM 

Proj Desc: The proposed development is to construct a 3,489 square foot building for a Chase Bank with with proposed pavement drive isles and twenty five (25) parking spaces (including one ADA parking space). The project includes water, wastewater, and reclaimed water connections to a developer provided utilities at the parcel boundary within World Commerce Center development.

DateTimeNote
8/20/2021 9:47 AM

emailed ATM c/s to ZCotton@marandbuilders.com

8/10/2021 8:54 AM

APPROVED
C2021-001573*001
ATM w/ Canopy

8/4/2021 4:37 PM

8/10/2021 8:54 AM

emailed approved Clearance sheet to Zack Cotton <ZCotton@marandbuilders.com>

4/29/2021 8:52 AM

Ready for Pre-Con Meeting

3/8/2021 2:52 PM

emailed FTP link w/ C/S to ahanna@core-states.com

3/8/2021 2:33 PM

APPROVED
C2021-001573-
3,489 SF Chase Bank W/ Drive Thru (Outparcel 2)

3/3/2021 1:58 PM Fee Email Sent to Applicant
3/3/2021 12:45 PM Fee Email Sent to Applicant
3/3/2021 10:04 AM Comments Sent to Applicant
3/3/2021 2:14 PM

APPROVED

2/25/2021 9:05 AM Comments Sent to Applicant
2/22/2021 8:31 AM Fee Email Sent to Applicant
2/22/2021 8:29 AM

Second Resubmittal 5-day review

2/22/2021 8:03 AM

Monday, February 22, 2021.  Digitally signed Civil and landscape plans that were received on 2/19/21 we validated by D. Willis.

2/19/2021 11:28 AM Comments Sent to Applicant
2/12/2021 8:32 AM

MODCP 20-99 has replaced COMM 2019-87. As-Built for that project will be needed before this project's Asbuilt plans can be approved.

2/9/2021 11:50 AM Comments Sent to Applicant
2/4/2021 1:48 PM

Tree Bank Fund Payment: $225.00 due

2/1/2021 10:32 AM

First Resubmittal 5-day review

1/29/2021 10:39 AM Comments Sent to Applicant
1/7/2021 7:09 AM Comments Sent to Applicant
1/5/2021 9:58 AM

COMM 2019-87 must be as-builted prior to approval of this project's as-built.

1/5/2021 9:48 AM

IMDP required to be submitted and approved prior to approval of this project.

12/22/2020 1:48 PM Fee Email Sent to Applicant
12/22/2020 1:51 PM

First Submittal 8-day review/DRC 1/13/2020/SJCU

12/22/2020 1:49 PM

Paving and Draining plans are not signed and sealed