St. Johns County Application Submittal Management

* Roadway Construction *

RW CONST   2020000015

Project Name: IGP Commerce Center

Parent Project: PUD-2018000003

Issue Date: 7/14/2020 Comp Date: 11/22/2021 smorrison

Applicant:

Owner:

Proj Desc: The proposed on-site improvements include the construction of an internal access road and stormwater management facility, to support the construction of 17 Industrial Lots.

DateTimeNote
10/17/2022 11:45 AM

SJC Environmental Staff spoke with Michael McLendon with Gulfstream Design Group on 10/17/22 regarding proposed changes to Landscape Plans. Staff recommended a MODCP for level of changes proposed. As-builts cannot be approved until any MODCPs are approved. - ARH 10/17/2022

7/13/2022 8:16 AM

A field change to the approved plans will be include on the asbuilt submitted for this project due to location of utilities. see email in ERMS

11/22/2021 1:23 PM

emailed FTP link to garrett@gulfstreamdesign.com and lindsay@gulfstreamdesign.com

11/22/2021 12:21 PM

APPROVED
printed inspectors copy

11/22/2021 12:06 PM

Open for Tech to address comment. (11/4/2021)

11/17/2021 1:28 PM

Sidewalk Fund and CIF fee paid with check # 100371

11/10/2021 4:21 PM Fee Email Sent to Applicant
11/10/2021 4:24 PM

added sidewalk fee of $94,900 per email (see erms)

11/4/2021 1:01 PM Comments Sent to Applicant
10/27/2021 2:07 PM

Bond received, processed, sent to comptroller

10/26/2021 7:34 AM Fee Email Sent to Applicant
10/26/2021 7:33 AM

Fifth Resubmittal 5-day review

10/21/2021 11:34 AM

Revised cost estimate approved (with 15%) at $2,485,161.50.  BPP

5/12/2021 10:22 AM Comments Sent to Applicant
5/4/2021 10:38 AM Fee Email Sent to Applicant
5/4/2021 10:45 AM

BOX 14

5/4/2021 10:37 AM

Fourth Resubmittal 5-day review

2/10/2021 7:11 AM Comments Sent to Applicant
2/8/2021 10:03 AM

02/08/2021 - PER TECHNICAL DIVISION:  This project will require bonding at the RW CONST phase and the PLAT phase.  Will need 2 separate cost estimates and bonds.

2/2/2021 8:29 AM Fee Email Sent to Applicant - 2nd and 3rd resubmittal fees
2/2/2021 8:26 AM

Third Resubmittal 5-day review

2/2/2021 8:25 AM

3 - Hard copy plans set required once application is approved, electronically signed and sealed (no digital signature to verify)

1/4/2021 7:34 AM Comments Sent to Applicant
12/22/2020 7:51 AM

Second Resubmittal 5-day review

10/30/2020 7:36 AM Comments Sent to Applicant
10/20/2020 8:31 AM

First Resubmittal 5-day review

10/7/2020 8:30 AM Project Description Updated
10/1/2020 10:16 AM Comments Sent to Applicant
10/1/2020 10:18 AM

Please remember to update applicant information when we receive the submittal from the new EOR. 

9/18/2020 4:32 PM

NEW ENGINEER TAKING OVER PROJECT - RE-ROUTE TO ALL DEPTS & FOR TIMEFRAME OF 1ST SUBMITTAL

8/4/2020 7:22 AM Comments Sent to Applicant
7/31/2020 2:28 PM

DRC 8/5/2020

7/14/2020 9:06 AM

First Submittal 8-day review/DRC 8/1/2020/SJCU/BOX 3